夯管工程穿越公路施工的技术工艺 |
| |
引用本文: | 卢高书,王新明,刘传壮.夯管工程穿越公路施工的技术工艺[J].交通标准化,2009(15):38-40. |
| |
作者姓名: | 卢高书 王新明 刘传壮 |
| |
作者单位: | [1]山东省泰安市公路局,山东泰安271000 [2]中铁十四局北京指挥部,北京101400 |
| |
摘 要: | 以DN1200热力管线过北京市四环主路夯管工程为例介绍夯管工程的施工工艺.并对施工过程中的注意事项和保证措施进行详细的阐述,可供同类工程参考。
|
关 键 词: | 夯管 施工 工艺 |
Tamper Pipe Project Traversing Highway Construction Technique |
| |
Institution: | LU Gao-shu, WANG Xin-ming, LIU Chuan-zhuang(1.Shandong Provincial Tai'an City Highway Bureau, Tai'an 271000, China; 2.Beijing Headquarters, China Railway 14th Group Corporation, Beijing 101400, China) |
| |
Abstract: | Taking DN1200 thermal pipe traversing the fourth ring main road tamper pipe in Beijing for example, the tamper pipe project construction technique is introduced. Furthermore, the items deserving attention and guaranteeing measures are elaborated in details so as to provide reference for technicians. |
| |
Keywords: | tamper pipe construction technique |
本文献已被 维普 等数据库收录! |
|