摘    要:框构桥顶进施工过程中由于地基处理不当或顶进中技术措施不到位,极容易出现扎头或扎尾问题,给施工造成很大的困难和影响。结合朔黄铁路K550+881处顶进桥施工中出现扎尾问题,分析了出现扎尾的原因,重点阐述了地基处理、梁体纠偏方案与工艺流程及施工过程中关键事项,为类似问题的处理提供借鉴经验。

关 键 词:框构桥  顶进  扎尾  纠偏

Tie Ends in Frame Bridge Jacking Construction
Qiao Zhuoxian. Tie Ends in Frame Bridge Jacking Construction[J]. Modern Urban Transit, 2012, 0(4): 37-39
Authors:Qiao Zhuoxian
Affiliation:Qiao Zhuoxian
Abstract:In the frame bridge jacking construction process, due to improper technical measures taken for formation treatment or jacking, the problem of tie head or tie end is very often seen, which causes great difficulty to the construction and has adverse impact. Taking into consideration of the bar-end problem in the jacking bridge construction at the K550+881 of Shuohuang Railway line, the paper analyzes the cause of tie ends, and it mainly introduces the foundation treatment, the beam correction programs and key issues in the process and construction, providing reference experience to deal with similar problems.
Keywords:frame bridge  jacking  tie end  correction