首页 | 本学科首页   官方微博 | 高级检索  
     

重载铁路隧道设计技术探讨
引用本文:赵晋友,周鲁,周书明. 重载铁路隧道设计技术探讨[J]. 隧道建设, 2012, 32(3): 336-340. DOI: 10.3973/j.issn.1672-741X.2012.03.013
作者姓名:赵晋友  周鲁  周书明
作者单位:(中铁隧道勘测设计院有限公司, 天津 300133)
摘    要:为解决重载运输条件下铁路隧道设计难题,通过大秦线铁路隧道病害的调查资料,对重载运输诱发的隧道病害及其原因进行总结分析。依托山西中南部铁路通道隧道设计经验,提出重载铁路:〖JP〗 1)软弱破碎围岩大于1000m或软岩高地应力段长大于500m的隧道、4km以上突水突泥风险等级较高的岩溶隧道优选采用2个单线隧道方案; 2)单线隧道仰拱矢跨比取1/6.5、双线取1/10.5,可以满足30t列车轴质量要求; 3)隧道内坡度不应小于3‰、富水地层不小于5‰,提出防排水措施实现运营可维护; 4)计算确定了轨下结构设计参数; 5)对隧道内轨道结构过渡、轨下及隧底结构过渡段采取了设计措施; 6)提出了隧道基底普查及承载要求。

关 键 词:重载铁路隧道  病害  设计技术  隧道结构  防排水  过渡段  
收稿时间:2012-02-27
修稿时间:2012-05-07

Discussion on Design of Heavy-haul Railway Tunnel
ZHAO Jinyou,ZHOU Lu,ZHOU Shuming. Discussion on Design of Heavy-haul Railway Tunnel[J]. Tunnel Construction, 2012, 32(3): 336-340. DOI: 10.3973/j.issn.1672-741X.2012.03.013
Authors:ZHAO Jinyou  ZHOU Lu  ZHOU Shuming
Affiliation:(China Railway Tunnel Survey & Design Institute Co., Ltd., Tianjin 300133, China)
Abstract:The diseases and their causes of tunnel induced by heavy-haul transportation are analyzed, with the disease data of tunnel on Datong-Qinhuangdao railway as examples. Conclusions drawn are as follows: 1 ) Two single-line tun- nels might be the best choice when karst tunnel with water and mud bursting section longer than 4 km and soft and weak surrounding rocks section longer than 1 000 m or section with soft rocks and high ground stress longer than 500 m. 2) Single-line tunnel crown with rise-span ratio of 1/6.5 and twin-line tunnel with rise-span ration of 1/10.5 can meet the running requirements. 3 ) The gradient in the tunnel should lower than 3%0, ground with rich water Should less than 5%0. Water draining technologies are presented. 4) The design parameters of the structure under the track bed are de- cided. 5 ) Countermeasures of the connection sections are adopted. 6 ) The general investigation and load bearing re- quirements of the tunnel foundation are proposed.
Keywords:heavy-haul railway tunnel  disease  design technology  tunnel structure  waterproofing and drainage  con- nection section
本文献已被 CNKI 维普 万方数据 等数据库收录!
点击此处可从《隧道建设》浏览原始摘要信息
点击此处可从《隧道建设》下载全文