施桥船闸下游停泊锚地工程预应力管桩施工工艺
引用本文:汪萍. 施桥船闸下游停泊锚地工程预应力管桩施工工艺[J]. 水运科技信息, 2014, 0(6): 140-142
作者姓名:汪萍
作者单位:扬州市航道管理处,扬州225003
摘    要:针对施桥船闸下游停泊锚地工程现场地质条件,对预应力管桩的沉桩工艺和管桩桩顶与底板的连接处理进行了研究,就送桩长度达6.38 m 如何控制沉桩的位置精度,以及在软土大开挖条件下如何减少地基表层裸露时间,保证桩顶与底板的连接质量,采取了有效措施,取得了良好的效果。

关 键 词:停泊锚地  预应力管桩  施工工艺

Construction Technology Research on Prestressed Pipe Pile of Shiqiao Shiplock Downstream Anchorage Engineering
Wang Ping. Construction Technology Research on Prestressed Pipe Pile of Shiqiao Shiplock Downstream Anchorage Engineering[J]. Transportation Science & Technology, 2014, 0(6): 140-142
Authors:Wang Ping
Affiliation:Wang Ping (Yangzhou Waterway Administration Office, Yangzhou 225003, China)
Abstract:Shiqiao Shiplock downstream anchorage engineering soil condition is very poor and the un-derground water level is high.The high strength PHC prestressed pipe pile for reinforcing soft soil foundation is adopted in the project.According to the characteristic condition,the pile sinking tech-nology and the treatment of pile top and bottom connection for prestressed concrete pipe pile are stud-ied.Effective measures to control the position accuracy of pile sinking when pile length up to 6.38m, reduce the surface exposed time and ensure the connection quality of pile top and bottom under the conditions of large excavation in soft soil foundation are performed and good effect has achieved.
Keywords:anchorage  prestressed pipe pile  construction technology