17万吨浮船坞两段建造法水上合拢对接工艺设计
引用本文:袁红莉,孙倩,刘建闽.17万吨浮船坞两段建造法水上合拢对接工艺设计[J].船舶工程,2018,40(10):88-92.
作者姓名:袁红莉  孙倩  刘建闽
作者单位:集美大学轮机工程学院,福建厦门,361021;集美大学轮机工程学院,福建厦门,361021;集美大学轮机工程学院,福建厦门,361021
基金项目:福建省自然科学基金项目:船舶薄板结构焊接变形机理与控制研究(2016J01249); 福建省自然科学基金项目:复杂海况下高速船舶动力特性数值方法研究(2018J01493)。
摘    要:由于船台限制,17万吨浮船坞无法在船台整体合拢。经过技术论证,采取将坞体分为前后两段分别建造,将浮箱甲板以下端部密封后下水,再在水上进行浮态对接;利用对接工装将坞体对接缝处的局部区域与水隔离,再进行焊接。此工艺操作难度较大,特别是前后段坞体对中调整。针对对中难度大的问题,研发快速定位工装,并编制详细的合拢过程控制操作程序,确保水上对接合拢的顺利进行。同时为其它大型船坞或船舶两段建造、水上合拢积累经验,为其它船舶修理改装、水上定位作业施工提供一定的借鉴和指导作用。

关 键 词:浮船坞  浮态合拢  对接工装  定位工装  两段建造法
收稿时间:2018/6/3 0:00:00
修稿时间:2018/11/22 0:00:00

Process Design of Floating Condition for 170000t Floating Dock Two-section-erection
Yuan hongli,Sun qian and Liu jianmin.Process Design of Floating Condition for 170000t Floating Dock Two-section-erection[J].Ship Engineering,2018,40(10):88-92.
Authors:Yuan hongli  Sun qian and Liu jianmin
Institution:Institute of marine engineering,Jimei university,Institute of marine engineering,Jimei university,Institute of marine engineering,Jimei university
Abstract:Due to the limitation of the shipway, 170000t floating dock can not be whole connected on the shipway. After technical argumentation, the dock body was divided into two sections, namely, the front and back sections. The structure below the end of the pontoon deck was sealed, then the dock launched from the shipway and docked on the water. Before welding, docking tools was used to isolate the local area of the dock from the water. This process is difficult, especially the alignment of the front and back sections of the dock body. In view of the difficult problems in the alignment, the rapid positioning fixture was developed and the detailed connection process control procedures were compiled to ensure the smooth erection on floating condition. At the same time, it can accumulate experience for the two-section-erection of other large docks or ships. It can provide some reference and guidance for other ship repair, modification and water positioning operation.
Keywords:floating  dock  floating  connection  docking  tool  positioning  Fixture  two-section-erection