船体分段制造网络计划最低成本日程 |
| |
引用本文: | 蔺士忠,许淼,吕波.船体分段制造网络计划最低成本日程[J].船海工程,2007,36(5):23-25. |
| |
作者姓名: | 蔺士忠 许淼 吕波 |
| |
作者单位: | 中国船舶工业综合技术经济研究院,北京,100081 |
| |
摘 要: | 基于压缩工序持续时间与成本的关系,提出了总成本最低时网络计划的最优工期模型——最低成本日程优化模型,并以船舶分段制造日程计划为应用对象验证了模型的有效性。
|
关 键 词: | 分段 网络计划 优化 |
文章编号: | 1671-7953(2007)05-0023-03 |
修稿时间: | 2006-11-29 |
The lowest budget schedule of block construction |
| |
Authors: | LIN Shi-zhong XU Miao LU Bo |
| |
Institution: | Technology Research and Economy Development Institute, CSSC, Beijing 100081, China |
| |
Abstract: | The project management of shipbuilding is a complicated system affected by numerous factors,which brings about the difficulty to control the duration and cost.Based on the relation between time and cost,an optimization model to find the lowest budget schedule of network planning is established under the assumption that the duration of process is flexible,and the validity of the model is verified in the scheduling of block construction. |
| |
Keywords: | block network scheduling optimization |