大跨度岩溶隧道施工工法比选
引用本文:陈明奎,申玉生,侯瑞彬.大跨度岩溶隧道施工工法比选[J].中南公路工程,2014(2):31-36.
作者姓名:陈明奎  申玉生  侯瑞彬
作者单位:西南交通大学 交通隧道工程教育部重点实验室,四川 成都610031
基金项目:国家自然科学基金(No.41102220、No.51178398);教育部创新团队发展计划资助(1RT0955);中央高校基本科研业务费专项资金(No.SWJTUCX014、No.SWJTU11ZT33)
摘    要:随着我国高速公路的发展,在岩溶地区修建隧道工程日益增多,选择合理施工工法是隧道施工安全稳定的重要一环。根据大跨度岩溶隧道中溶腔的发育程度、发育位置以及溶腔内充填物性质的不同,隧道需采用不同施工工法。以乐昌至广州高速公路段某大跨度岩溶隧道为例,采用有限元软件对其进行了三台阶法、单侧壁导坑法和双侧壁导坑法等3种施工工法的比选。最后得出结论:双侧壁导坑法在岩溶隧道施工中能有效的控制围岩塑性区的发展和洞周位移,并且能够有效改善围岩的受力状态,适当提高衬砌的应力水平,是较为合理的施工工法。可为岩溶地区高速公路隧道设计施工提供一定的参考。

关 键 词:岩溶隧道  施工优化  数值计算  高速公路

Comparison of the Construction Methods of Longspan Karst Tunnel
CHEN Mingkui,SHEN Yusheng,HOU Ruibin.Comparison of the Construction Methods of Longspan Karst Tunnel[J].Central South Highway Engineering,2014(2):31-36.
Authors:CHEN Mingkui  SHEN Yusheng  HOU Ruibin
Institution:(MOE Key Laboratory of Transportation Tunnel Engineering, Southwest Jiaotong University, Chengdu, Sichuan 610031, China)
Abstract:There are more and more Karst tunnels to be constructed in our country,the construc-tion methods of Karst tunnel are also increasingly diverse.Choosing reasonable construction method is one of the most important aspects of security.Different construction methods should be used depending on location ,degree and the property of the fillers of the longspan karst cavity.In background of a certain Karst tunnel in the expressway from Lechang to Guangzhou,the author simulated three construction meth-ods:the three steps method,single-side-drift method and double-side-drift method using the finite ele-ment software Abaqus,and analysed the formation and development of the plastic zone and the displace-ment of the surrounding rock,and come to the conclusion:double-side-drift method can not only control the development of the plastic zone and the displacement of the surrounding rocks,but also can can effec-tively improve the stress of surrounding rock,appropriately raise the level of stress of the lining.It is the proper construction method for Cavity Karst Tunnel.The conclusion provide reference for tunnel construc-tion under similar conditions.
Keywords:karst tunnel  numerical simulation  three steps method  single-side-drift method  double-side-drift method