乌鞘岭隧道7号斜井涌水治理措施
引用本文:董勤银. 乌鞘岭隧道7号斜井涌水治理措施[J]. 隧道建设, 2005, 25(6): 32-35
作者姓名:董勤银
作者单位:铁道部工程管理中心乌鞘岭隧道建设指挥部,兰州,730000
摘    要:介绍了乌鞘岭隧道7号斜井在施工期间发生突然涌水后的堵水注浆参数、泵站配置能力以及斜井拐弯避开涌水地段的措施,说明了治水效果,可供以后隧道施工中发生涌水治理的设计与施工参考。

关 键 词:隧道 涌水 治理
收稿时间:2005-11-18
修稿时间:2005-11-18

Countermeasures for Water Inflow into No. 7 Inclined Shaft of |Wushaoling Tunnel
DONG Qin-ying. Countermeasures for Water Inflow into No. 7 Inclined Shaft of |Wushaoling Tunnel[J]. Tunnel Construction, 2005, 25(6): 32-35
Authors:DONG Qin-ying
Affiliation:Wushaoling Tunnel Construction Headquarters of Engineering Management Center under Ministry of Railways of china, Lanzhou 730000, Gansu, China
Abstract:This paper introduces the parameters of grouting to control the water inrush of No.7 inclined shaft of Wushaoling tunnel, the capacity determination of the pumping stations, the changing of the route of the inclined shaft to avoid the water inrush area, and the  effects of the  water inrush control, which can offer reference for the design and execution of  water inrush control during tunnel construction.
Keywords:tunnel water inrush countermeasure