地铁隧道下穿酒店大楼施工方案调整与监测分析
引用本文:尚艳亮. 地铁隧道下穿酒店大楼施工方案调整与监测分析[J]. 国防交通工程与技术, 2006, 4(1): 45-48
作者姓名:尚艳亮
作者单位:石家庄铁道学院,河北,石家庄,050043
摘    要:针对华师站至岗顶站地铁隧道下穿岗顶酒店大楼施工中存在的某些问题,选择了适当的施工方案,进行了现场监控量测,并对监测结果进行了分析,确保了地铁施工通过酒店大楼时的安全,对今后类似工程有一定的借鉴作用。

关 键 词:隧道  施工方案  监测分析
文章编号:1672-3953(2006)01-0045-04
收稿时间:2005-10-28
修稿时间:2005-10-28

Investigation of the Construction Plan for the Tunnel and Monitoring of the Hotel Building During the Underground Tunnel Construction
SHANG Yan-liang. Investigation of the Construction Plan for the Tunnel and Monitoring of the Hotel Building During the Underground Tunnel Construction[J]. Traffic Engineering and Technology for National Defence, 2006, 4(1): 45-48
Authors:SHANG Yan-liang
Affiliation:The School of Civil Engineering, the Shijiazhuang Railway Institute, Shijiazhuang 050043,China
Abstract:A suitable construction plan is put forward in the paper according to the series of problems in passing through the Gangding Hotel underground during the Huashi-Gangding tunnel construction. Monitoring and survey are carried out and the measured data are analyzed. The safety of the Gangding Hotel is ensured. The project may serve as a reference for other similar ones.
Keywords:tunnel  construction plan  monitor and survey