高原高寒高应力板岩施工技术研究
引用本文:高颖.高原高寒高应力板岩施工技术研究[J].铁道建筑技术,2011(12):51-56.
作者姓名:高颖
作者单位:中国铁建十八局集团第三有限工程公司,河北涿州,072750
摘    要:高原高寒高应力板岩隧道监控量测技术,能及时地掌握围岩动态的变化,随时监控到围岩的变形情况。根据监测结果指导隧道施工,提前做好隧道的大变形和坍塌掉块的预防和加固工作,为施工单位在高应力板岩施工方面提供一些参考经验。

关 键 词:高原高寒  高应力  板岩  监控量测  动态变化

Study on High Stressed Alpine Plateau Slate Construction Technology
Gao Ying.Study on High Stressed Alpine Plateau Slate Construction Technology[J].Railway Construction Technology,2011(12):51-56.
Authors:Gao Ying
Institution:Gao Ying (China Railway 18th Bureau Group Co.Ltd.,Zhuozhou 072750,China)
Abstract:Stressed slate of high alpine plateau tunnel technology is a brand new monitoring and measuring for tunnel high stress,which makes timely prehension of rock change and monitoring of the deformation of the surrounding rock a reality.And henceforth provide scientific and convincing evidence for timely Guidance for the tunnel construction.Therefore it will surely help in large deformation and collapse prevention.Thus provide reference construction enterprises in the construction of high stressed slate.
Keywords:alpine plateau  high stress  slate  monitoring and measuring  dynamic change