公路隧道近距离下穿电力管线施工技术研究
引用本文:吴文娟,王振飞. 公路隧道近距离下穿电力管线施工技术研究[J]. 城市道桥与防洪, 2021, 0(5): 220-225. DOI: 10.16799/j.cnki.csdqyfh.2021.05.065
作者姓名:吴文娟  王振飞
作者单位:中铁隧道股份有限公司,河南郑州450001
摘    要:为解决杭州市香积寺路西延工程盾构段下穿220 kV半霞线线、半霞线电力管沟横穿东侧明挖段隧道基坑(4#工作井)及燃霞、燃湾线电力管沟与中间明挖隧道基坑呈“L”形交叉等施工难题,首先,通过对盾构施工的影响范围、地表隆陷变化规律以及电力管沟对地表变形适应能力评估的研究,采取优化掘进参数、控制泥水压力、掘进速度、出渣量、盾构...

关 键 词:公路隧道  电力管线  原地保护  控制措施  沉降监测

Research on Construction Technology of Highway Tunnel under Electric Power Pipeline in Short Distance
WU Wenjuan,WANG Zhenfei. Research on Construction Technology of Highway Tunnel under Electric Power Pipeline in Short Distance[J]. Urban Roads Bridges & Flood Control, 2021, 0(5): 220-225. DOI: 10.16799/j.cnki.csdqyfh.2021.05.065
Authors:WU Wenjuan  WANG Zhenfei
Abstract:In order to solve the construction problems of the shield section of Xiangjisi Road West Extension Project in Hangzhou passing under 220 kV Banxia Line, the power pipe trench of Banxia Line crossing the foundation pit (4# working shaft) of the tunnel at the east side of excavating section and the L-shaped intersection between the power pipe trenches of Ranxia Line and Ranwan Line and the foundation pit of the tunnel ate middle excavation, firstly, through the study on the influence scope of shield construction, the change law of surface heave and subsidence, and the evaluation of the adaptability of power pipe trench to surface deformation, the measures of optimizing tunneling parameters, controlling slurry pressure, tunneling speed, slag discharge, shield deviation correction, synchronous and secondary grouting are taken to protect the pipelines. Secondly, in order to reduce the construction difficulties, the on-site protection measures of steel I-beam jacking concrete cable trench and reinforced concrete cover plate supporting power pipe trench are adopted to protect the pipeline. After taking reasonable construction protection measures for 220 kV power pipeline, the excavation of the foundation pit of the tunnel is successful, and the shield starts on time, which not only saves the cost, but also shortens the construction period, and also provides a reference for the construction of similar projects in the future.
Keywords:highway tunnel   power pipeline   in-situ protection   control measures   settlement monitoring