土压/泥水平衡双模式盾构适应性设计
引用本文:王百泉,左龙,刘永胜,孟鑑先.土压/泥水平衡双模式盾构适应性设计[J].隧道建设,2020,40(Z2):314-318.
作者姓名:王百泉  左龙  刘永胜  孟鑑先
作者单位:(1. 中铁隧道局集团有限公司, 广东 广州 511458; 2. 中铁隧道勘察设计研究院有限公司, 广东 广州 511458;3. 广东省隧道结构智能监控与维护企业重点实验室, 广东 广州 511458; 4. 中铁隧道股份有限公司, 河南 郑州 450001)
摘    要:为解决复杂地质及周边环境盾构设备选型难题,结合多模式盾构的发展与研究现状,对多模式盾构进行了定义与分类,主要分为土压/泥水双模式盾构、土压/TBM双模式盾构、泥水/TBM双模式盾构等几大类型。并结合南宁市轨道交通5号线一期工程,对土压/泥水平衡双模式盾构的主要工作原理、特点、适用范围及适应性设计等方面进行了分析,结果表明: 土压/泥水平衡模式盾构地质适应性广、设备利用率高、施工成本低,解决了同一区间不同地质环境条件下盾构设备选型的问题,在一定程度上为地质复杂、工程敏感地带提供了一套可靠解决方案。


Adaptive Design of Earth Pressure/Slurry Balance Dual mode Shield Machine
WANG Baiquan,ZUO Long,LIU Yongsheng,MENG Jianxian.Adaptive Design of Earth Pressure/Slurry Balance Dual mode Shield Machine[J].Tunnel Construction,2020,40(Z2):314-318.
Authors:WANG Baiquan  ZUO Long  LIU Yongsheng  MENG Jianxian
Institution:(1. China Railway Tunnel Group Co.,Ltd., Guangzhou 511458, Guangdong, China; 2. China Railway Tunnel Consultants Co., Ltd., Guangzhou 511458, Guangdong, China; 3. Guangdong Provincial Key Laboratory of Intelligent Monitoring and Maintenance of Tunnel Structure, Guangzhou 511458, Guangdong, China; 4. China Railway Tunnel Stock Co., Ltd., Zhengzhou 450001, Henan, China)
Abstract:In order to solve the problem of shield equipment selection in complex geology and surrounding environment, the paper defines and classifies multi mode shield according to its development and research status. It is mainly divided into several types, such as earth pressure/mud water dual mode shield, earth pressure/TBM dual mode shield, mud water/TBM dual mode shield. And then combined with the first phase project of Nanning rail transit line 5, the main working principle, characteristics, applicable scope and adaptive design of earth pressure/slurry balance dual mode shield machine are analyzed. The results show that : The earth pressure/mud water balance shield has wide geological adaptability, high equipment utilization ratio and low construction cost, which solves the problem of shield equipment selection under different geological conditions in the same section. To a certain extent, it provides a set of reliable solution for the geological complex and engineering sensitive zone.
Keywords: