温州洪溪特大桥总体设计
引用本文:戴显荣,叶雨清.温州洪溪特大桥总体设计[J].桥梁建设,2021(2):99-104.
作者姓名:戴显荣  叶雨清
作者单位:浙江省交通规划设计研究院
基金项目:浙江省交通运输厅科技计划项目(2015J02)。
摘    要:浙江温州洪溪特大桥为(150+265+150)m双塔双索面矮塔斜拉桥,左、右分幅设计.针对峡谷风环境复杂、基本风速高、主墩高的特点,采用塔墩梁固结体系,提高了桥梁整体刚度和抗风性能;主梁采用单箱双室斜腹板变截面预应力箱梁,顶宽15.25 m,跨中梁高4.5 m、根部梁高9.2 m;桥塔采用Y形塔,由上、中、下塔柱组成,...

关 键 词:矮塔斜拉桥  分幅  塔墩梁固结体系  变截面预应力箱梁  高墩  Y形桥塔  静、动力性能  桥梁设计

Overall Design of Hongxi Bridge in Wenzhou
DAI Xian-rong,YE Yu-qing.Overall Design of Hongxi Bridge in Wenzhou[J].Bridge Construction,2021(2):99-104.
Authors:DAI Xian-rong  YE Yu-qing
Institution:(Zhejiang Provincial Institute of Communications Planning,Design&Research,Hangzhou 310030,China)
Abstract:The Hongxi Bridge in Wenzhou,Zhejiang Province is a twin-deck extradosed bridge.The bridge has two pylons,creating three spans of 150,265 and 150 m.The stay cables are fanned out in double cable planes.To suit the aggressive environment and particular structural characterisitics of the bridge,including the complicated wind conditions,high fundamental wind speeds and high-rise main piers,a pylon-girder-pier fixed connection is used to improve the integral rigidity and wind resistance of the bridge.The superstructure,consisting of two-cell prestressed concrete box girders with oblique webs,varies in depth from 4.5 m at the midspan to 9.2 m over the piers.The top of the box girders measures 15.25 m.The pylons are Y-shaped reinforced concrete structures with upper,intermediate and lower columns,rising 170.2 to 175.2 m at full height,and 42.0 m above the deck.The stay cables,which are formed of finished steel strands with nominal tensile strength of 1860 MPa,are anchored to the pylons via the saddles with individual tubes and anchored to the girders via wedges under the flanges.The foundation of each pylon incorporates 15,?2.5 m end-bearing piles and a rectangular pile cap.The abutments are gravity structure sopported on spread foundations.The pylons were constructed using climbing formwork,the prestressed concrete box girders were cast in situ in cantilevers using form travelers.The closure section was constructed with the assistance of lifting frames,before closing,2000 kN jacking and pushing force was applied at the closure gap.The spatial finite element model of the overall bridge was established by MIDAS Civil for static and dynamic analysis.The results demonstrate that the static and dynamic performance of all the components can meet the code requirements.
Keywords:extradosed bridge  twin-deck  pylon-pier-girder fixed connection  prestressed box girder with variable cross-section  high-rise pier  Y-shaped pylon  static and dynamic analysis  bridge design