贵瓮高速公路建中隧道施工难点及治理措施
引用本文:齐俊,孙毅,戴李春,李国文,杨永斌.贵瓮高速公路建中隧道施工难点及治理措施[J].铁道标准设计通讯,2015(2):87-90.
作者姓名:齐俊  孙毅  戴李春  李国文  杨永斌
作者单位:1. 北京交通大学城市地下工程教育部重点实验室,北京,100044
2. 贵州中交贵瓮高速公路有限公司,贵州瓮安,550400
3. 中交公路规划设计院有限公司,北京,100088
4. 中交第二公路工程局有限公司,西安,710065
基金项目:中央高校基本科研业务费专项资金资助
摘    要:溶腔、洞室和软弱破碎带是岩溶地区隧道施工的难点和重点。贵瓮高速建中隧道在施工过程中出现了围岩与设计情况不符以及溶洞塌方等问题,严重影响了施工进度。为此,通过对国内典型岩溶隧道设计施工案例进行分析借鉴,结合建中隧道的工程地质条件,在围岩与设计情况不符段进行方案修改,加强支护;在溶洞塌方段进行掌子面封闭、深孔注浆、回填混凝土等治理措施。经采取上述措施后,拱顶沉降和隧道周边位移均小于控制标准,效果良好。

关 键 词:公路隧道  岩溶空洞  超前地质预报

Construction Difficulties and Treatment Measures of Jianzhong Tunnel on Guiweng Highway
Qi Jun,Sun Yi,Dai Li-chun,Li Guo-wen,Yang Yong-bin.Construction Difficulties and Treatment Measures of Jianzhong Tunnel on Guiweng Highway[J].Railway Standard Design,2015(2):87-90.
Authors:Qi Jun  Sun Yi  Dai Li-chun  Li Guo-wen  Yang Yong-bin
Institution:Qi Jun;Sun Yi;Dai Li-chun;Li Guo-wen;Yang Yong-bin;Tunnel and Underground Engineering Research Center of Ministry of Education,Beijing Jiaotong University;China Communications Construction Company Guiweng Highway Company Limited;China Communications Construction Company Highway Consultant Company Limited;China Communications Construction Company Second Highway Engineering Company Limited;
Abstract:Dissolved cavity,cavern,soft and shear zone are difficult points in the construction of karst tunnels. During the construction of Jianzhong tunnel on Guiweng highway,great differences appeared between the local surrounding rock conditions and those indicated in the design and some caverns were collapsed. These seriously affected the construction progress. Therefore,through analyzing the domestic typical karst tunnel design and construction cases,based on the engineering geological conditions of Jianzhong tunnel,programs in the area with conflicted surrounding conditions against the design are modified with reinforced support. In the area of dissolved cavern collapse,such measures are taken as tunnel face closing,deep hole grouting and concrete backfilling. With the measures taken,crown settlement and tunnel inner perimeter displacement are less than the control limits and the effect is good.
Keywords:Highway tunnel  Dissolved cavity  Advance geological forecast