唐山港曹妃甸港区矿石码头三期工程码头平面布置
引用本文:许健刚,魏美芳. 唐山港曹妃甸港区矿石码头三期工程码头平面布置[J]. 港工技术, 2020, 0(2): 27-29
作者姓名:许健刚  魏美芳
作者单位:中交第一航务工程勘察设计院有限公司
摘    要:针对曹妃甸矿石码头三期工程,通过数学模型和物理模型试验,合理确定码头方位和长度。并针对船舶横移量较大的问题,对系缆墩的布置进行优化,减少了风、浪、流组合作用下船舶运动量对装卸作业的影响,且缆绳的受力更加均匀。

关 键 词:曹妃甸  矿石码头  平面布置  优化设计

Plane Layout of Ore Terminal Phase-3 Project at Caofeidian Harbor of Tangshan Port
Xu Jian’gang,Wei Meifang. Plane Layout of Ore Terminal Phase-3 Project at Caofeidian Harbor of Tangshan Port[J]. Port Engineering Technology, 2020, 0(2): 27-29
Authors:Xu Jian’gang  Wei Meifang
Affiliation:(CCCC First Harbor Consultants Co.,Ltd.,Tianjin 300222,China)
Abstract:In ore terminal Phase-3 project at Caofeidian harbor,the mathematical and physical models are used to determine the rational position and berth length of the terminal.In order to solve the problem of much more transverse distance of vessels,the layout of mooring piers is optimized to reduce the impact of vessels’motion on the load/unload operation under the combined action of wind,wave and ocean current,in addition,the cables are evenly stressed.
Keywords:Caofeidian  ore terminal  plane layout  design optimization