大吨位箱梁单点顶推技术探讨
引用本文:金绍龙. 大吨位箱梁单点顶推技术探讨[J]. 铁道建筑技术, 2013, 0(11): 12-14
作者姓名:金绍龙
作者单位:中铁二十五局集团第二工程有限公司,湖南衡阳412000
摘    要:顶推法是顶推桥梁施工工法中常用的施工方法,但大吨位箱梁单点顶推施工国内较为少见.通过长沙湘府路湘江大桥跨京广铁路联主跨箱梁顶推施工实践,较为详细地总结了大吨位箱梁顸推施工中临时墩布置、滑道设置、纠偏限位控制、导梁安装及后锚点等结构体系的设置要点与施工过程中关键工序的控制要点.

关 键 词:大吨位箱梁  单点顶推  限位装置  导梁  后锚点

Discussion on Single Point of Pushing Method for Large Tonnage Box Girder
Jin Shaolong. Discussion on Single Point of Pushing Method for Large Tonnage Box Girder[J]. Railway Construction Technology, 2013, 0(11): 12-14
Authors:Jin Shaolong
Affiliation:Jin Shaolong (China Railway 25^th Bureau Group Co. Ltd. , Hengyang 412000, China)
Abstract:Incremental launching method is commonly used in bridge construction, but large bridge incremental launching method is rarely seen at home. Through the practice of the Xiangjiang River Bridge construction, the author gives a detailed summary of the girder structure, slideway design, deviation control, launching guide beam as well as the anchoring point design in incremental launching construction together with the control point of the key procedure.
Keywords:large tonnage box girder  a single point of pushing  limit switch  guide beam  back anchorage zone