软弱富水地层大直径盾构始发端头联合加固方法及应用
引用本文:赵合全.软弱富水地层大直径盾构始发端头联合加固方法及应用[J].都市快轨交通,2022,35(2):130-135.
作者姓名:赵合全
作者单位:中铁十四局集团大盾构工程有限公司,南京211899
摘    要:盾构在高水头粉土粉砂及淤泥地层始发时易出现各种安全事故,工程上常采用地表注浆、地层冻结 等方法预先对始发端地层进行加固处理。结合杭州望江路盾构隧道地层特点,提出一种三轴搅拌桩、高压 旋喷桩及局部垂直冻结相结合的联合加固方法,并系统介绍该方法加固参数的确定和加固效果评价。现场 检测表明,各项条件均满足设计要求,盾构顺利始发,以期为类似工程提供借鉴。

关 键 词:轨道交通  盾构隧道  始发端头  局部垂直冻结法  三轴搅拌桩  高压旋喷桩

Combined Ground Improvement Method and Application of Shield Launching Hole in Soft and Watery Strata
ZHAO Hequan.Combined Ground Improvement Method and Application of Shield Launching Hole in Soft and Watery Strata[J].Urban Rapid Rail Transit,2022,35(2):130-135.
Authors:ZHAO Hequan
Institution:China Railway 14th Bureau Group Shield Engineering Co., Ltd
Abstract:Accidents are likely to occur when shield tunnels are launched in high water head and silty strata. Surface grouting, freezing, and other methods are often used to pre-strengthen the initial strata at the shield launching hole. Combined with the strata characteristics in the Wangjiang road tunnel, this study proposes a combined ground improvement of triaxial mixing piles, high-pressure jet grouting piles, and partial vertical freezing. This paper introduces the determination principle of the reinforcement parameters and effect evaluation. Field tests showed that all conditions met the design requirements. The tunnel was launched successfully and can be used as a reference for similar projects.
Keywords:rail transit  shield tunnel  launching hole  partial vertical freezing  triaxial mixing pile  high-pressure jet grouting pile