首页 | 本学科首页   官方微博 | 高级检索  
     检索      

无锡市高浪快速路总体设计
引用本文:陆沁.无锡市高浪快速路总体设计[J].城市道桥与防洪,2021(6):21-24.
作者姓名:陆沁
作者单位:上海市政工程设计研究总院(集团)有限公司,上海市200092
摘    要:为满足无锡市太湖新城出入交通需求,对无锡市高浪快速路总体设计方案进行研究.介绍了无锡市高浪快速路工程的建设背景、建设规模、沿线现状及规划用地情况,明确了项目的功能定位、服务对象及建设标准.在对无锡市现状路网流量调查分析的基础上,结合规划成果,采用四阶段法对交通量进行了预测.结合交通功能及地块开发情况,研究分析了项目总体方案和项目沿线节点实施方案.最后总结认为,高浪路位于太湖新城核心区,项目规模大、等级高、社会关注度高,设计时须统筹考虑快速路敷设形式、节点处理方案、地面辅路的交通组织等问题,以实现经济效益与社会效益最大化.

关 键 词:快速路  总体设计  连续隧道  节点方案
收稿时间:2021/3/28 0:00:00

Overall Design of Gaolang Expressway in Wuxi
LU Qin.Overall Design of Gaolang Expressway in Wuxi[J].Urban Roads Bridges & Flood Control,2021(6):21-24.
Authors:LU Qin
Abstract:In order to meet the traffic demands into and out of Taihu New Town in Wuxi, the overall design scheme of Gaolang Expressway is Wuxi is studied. The construction background, construction scale, present situation along line and planning land of Wuxi Gaolang Expressway Project are introduced. The functional orientation, service object and construction standard of the project are made clearly. On the basis of the flow investigation and analysis of the current road network in Wuxi, and combined with the planning effects, the four-stage method is used to predict the traffic flow. Combined with the traffic functions and the land development conditions, the overall scheme and the node implementation scheme along the along of the project are studied and analyzed. Finally, the conclusion shows that the project scale is large, the grade is high and the social attention is high because of Gaolang Road located in the core area of Taihu New Town. Therefore, the expressway laying type, node treatment scheme, traffic organization of ground auxiliary road and the other problems must be planned as a whole in order to realize the maximum economic benefit and social benefit.
Keywords:expressway  overall design  continuous tunnel  node scheme
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《城市道桥与防洪》浏览原始摘要信息
点击此处可从《城市道桥与防洪》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号