非确定因素影响下离散时段公路施工区用户费用模型
引用本文:杨琦, 杨云峰, 武大勇, 赵现伟. 非确定因素影响下离散时段公路施工区用户费用模型[J]. 交通运输工程学报, 2014, 14(1): 97-102.
作者姓名:杨  琦  杨云峰  武大勇  赵现伟
作者单位:1.长安大学 经济与管理学院,陕西 西安 710064;;2.陕西交通职业技术学院,陕西 西安 710018;;3.德克萨斯理工大学 土木与环境工程系,德克萨斯 卢伯克 79409
基金项目:国家自然科学基金项目51278057 交通运输部西部交通科技建设项目20113188201420 中央高校基本科研业务费专项资金项目2013G1221025 中央高校基本科研业务费专项资金项目2013G1221026
摘    要:
分析了离散时段下高速公路施工区的交通状况, 通过离散施工时段, 比较了各时间段内施工区容量和交通需求的关系, 建立了各个时间段相应的用户费用计算模型。分析了高速公路施工区用户费用的非确定因素, 根据非确定因素的概率分布值, 通过蒙特卡罗模拟对用户费用的波动区间进行预测, 并以清连高速公路为例进行实例验证。计算结果表明: 应用提出的模型, 白天施工时段的用户费用均值为193 148 021元, 最大值与最小值分别为466 820 060、117 342 849元, 夜晚施工时段的用户费用均值为1 795 047元, 最大值与最小值分别为3 443 468、1 417 274元。提出的模型能更好地体现非确定因素的影响。

关 键 词:交通运输经济   施工区   用户费用   蒙特卡罗方法   非确定因素   离散时段
收稿时间:2013-08-18

User cost model of highway work zone during discrete periods under influence of uncertain factors
YANG Qi, YANG Yun-feng, WU Da-yong, ZHAO Xian-wei. User cost model of highway work zone during discrete periods under influence of uncertain factors[J]. Journal of Traffic and Transportation Engineering, 2014, 14(1): 97-102.
Authors:YANG Qi  YANG Yun-feng  WU Da-yong  ZHAO Xian-wei
Affiliation:1. School of Economics and Management, Chang'an University, Xi'an 710064, Shaanxi, China;;2. Shaanxi College of Communications Technology, Xi'an 710018, Shaanxi, China;;3. Department of Civil and Environmental Engineering, Texas Tech University, Lubbock 79409, Texas, USA
Abstract:
The traffic situation of highway work zone during discrete periods was analyzed. By dispersing the work periods, the relationships between the capacities of work zones and user costs during different discrete periods were compared, and the calculation models of user costs during corresponding periods were set up. The uncertain factors of user cost for highway work zone were analyzed. Based on the probability distributions of uncertain factors, the fluctuation scope of user cost was predicted by using Monte Carlo simulation and verified by the example of Qinglian Highway. Calculation result indicates by using the proposed model, the average user cost under the day-time work scheme is 193 148 021 yuan, and the maximum and minimum costs are 466 820 060, 117 342 849 yuan respectively. The average user cost under the night-time work scheme is 1 795 047 yuan, and the maximum and minimum costs are 3 443 468, 1 417 274 yuan respectively. It is found that the application of proposed model can show the influences of uncertain factors well.
Keywords:transportation economy  work zone  user cost  Monte Carlo method  uncertain factor  discrete period