1.
商合杭铁路芜湖长江公铁大桥主桥为主跨588m的双塔双索面高低塔箱桁组合梁斜拉桥,该桥钢主梁采用箱桁组合结构。主桥钢梁节段船运至桥位,在主墩墩旁搭设简易钢支架,采用1 000t浮吊吊装、拖拉滑移法架设主墩墩顶节段钢梁;拼装800t变幅式桅杆起重机后双悬臂架设钢梁至辅助墩;辅助墩墩顶钢梁采用800t浮吊吊装架设,桥面架梁吊机再悬臂架设钢梁至边墩,将边墩墩顶钢梁分层叠放后再依次用架梁吊机吊装就位;中跨合龙段利用无为侧架梁吊机提升,采取部分斜拉索索力调整、桥塔墩墩顶顶推纵移、温差调整等措施,实现了高精度、快速顺利合龙。 相似文献
2.
平潭海峡公铁大桥大小练岛水道桥为主跨336m的双塔双索面钢桁梁斜拉桥。桥塔采用H形钢筋混凝土结构、高152m,桥塔墩采用直径4.4m的钻孔桩基础,采用圆端哑铃形高桩承台;主梁采用带副桁的正交异性板钢桁梁结构,主桁采用N形桁式,桁高13.5m、桁宽15m。该桥基础采用长栈桥和施工平台方案施工;钻孔桩采用KTY4000型液压动力头钻机施工;承台采用双壁钢吊箱围堰施工;桥塔塔柱采用ACF-125型全封闭液压爬模施工,标准施工节段高6m,索塔锚固区采用低回缩环向预应力锚固体系、二次张拉工艺施工。边跨、辅助跨钢桁梁在工厂内组拼成整体大节段,现场采用浮吊整体吊装;墩顶钢梁节段采用浮吊分节段架设;中跨钢梁节段采用1 100t架梁吊机单悬臂架设。 相似文献
3.
沪苏通长江公铁大桥主航道桥为主跨1 092m的双塔钢桁梁斜拉桥,大桥上层为6线公路、下层为4线铁路,主梁采用三主桁N形桁架结构,采用Q370qE、Q420qE与Q500qE 3种规格的高强桥梁结构钢。铁路桥面采用钢箱结构,公路桥面采用钢正交异性板结构。主桥钢桁梁采用大节段整体制造、架设,最大节段重1 744t。钢桁梁在工厂先加工制造杆件和板单元,再组拼成桁片和桥面板;然后在胎架上按"1+3"立体匹配组拼成大节段,整体船运至现场;墩顶节段采用1 800t浮吊架设,其余标准节段采用1 800t架梁吊机双悬臂对称架设;主跨钢梁采用纵移、压重、纵向与横向对拉等措施实现了精确合龙。 相似文献
4.
新建商合杭铁路芜湖长江公铁大桥主桥为(99.3+238+588+224+85.3)m的钢箱板桁结合梁斜拉桥,主梁上层为板桁结合,下层为钢箱结合钢桁梁。该桥钢梁划分为89个铁路面梁段单元和94个公路面梁段单元,采用分段吊装施工,钢梁架设采用"浮吊辅助架设墩顶节段+桥面架梁吊机悬臂架设"的总体方案,设中跨合龙口。首先利用浮吊起吊,采用支架法架设2号和3号桥塔墩墩顶的3个钢梁节段,然后在公路桥面上各安装2台桥面架梁吊机进行双悬臂架设,悬臂架设至辅助墩前方时,利用浮吊起吊安装辅助墩墩顶钢梁节段;当悬臂架设至边墩前方时,采用"浮吊+支架"辅助桥面架梁吊机悬臂架设边墩墩顶钢梁节段;最后利用2号墩侧架梁吊机提升中跨合龙段进行中跨合龙。 相似文献
5.
蒙华铁路洞庭湖特大桥主桥为主跨406m的三塔斜拉桥,主梁采用钢箱-钢桁组合结构。其中,下部钢箱梁宽21m,中心处梁高2.5m;上部钢桁梁采用华伦式布置,节间长14m,桁高12m。该桥主梁采用"先箱后桁"的方案施工,先安装下部钢箱梁,钢箱梁合龙后,在其顶面分组安装钢桁梁。边跨钢箱梁采用顶推法架设;主跨钢箱梁采用悬臂拼装法架设,钢箱梁节段利用300t架梁吊机整体吊装,在主跨跨中采用主动合龙方式合龙。上部钢桁梁杆件采用上弦杆制造长度修正、分组架设(5个节间为1组)、多个调整口合龙等技术施工,完成钢桁梁杆件拼装,并实现精确合龙。 相似文献
6.
G3铜陵长江公铁大桥主桥为(127.5+131+988+131+127.5) m公铁两用斜拉-悬索协作体系桥,双层桥面布置,上层为高速公路,下层为普速铁路与城际铁路。主梁为两主桁钢桁梁结构,采用三角形桁式,桁高13.5 m,桁宽35.0 m。上、下弦杆采用箱形截面,腹杆采用H形、王字形(腹板带肋H形)和箱形截面。上、下层桥面采用正交异性钢桥面板(下层压重区域采用整箱)与主桁形成板(箱)桁组合结构。为改善主桁节点受力,将腹杆的腹板在节点内延至上弦杆底板和下弦杆顶板。斜拉索和吊索的交叉区梁上锚固点采用纵向错开、横向偏移布置。采用有限元软件对结构进行整体和局部计算,结果表明:结构设计满足规范要求。主梁节段为全焊结构,边跨采用顶推施工,中跨斜拉段采用架梁吊机单悬臂施工,悬吊段采用缆载吊机由跨中向桥塔方向安装,合龙段设在斜拉-悬吊交叉区。 相似文献
7.
银西高铁银川机场黄河特大桥采用2孔96m简支钢桁梁和2联3×168m连续钢桁梁柔性拱结构,主桁横截面采用有竖杆的三角形桁式。钢桁梁采用半悬臂法施工,其中连续钢桁梁通过70t全回转架梁吊机自中跨跨中截面开始向两边跨对称架设,中跨主桁架设后安装60t全回转架拱吊机架设中拱,2孔96m简支钢桁梁各采用1台履带吊逐节拼装。施工中,临时墩顶设置竖向千斤顶,钢梁架设至临时墩顶时可调整标高;利用70t全回转架梁吊机调整悬臂节间的标高;主墩顶设置调落梁装置,成桥后整体调落梁。该桥于2017年9月30日落梁成桥,架设过程质量安全可控,柔性拱实现了无外力自然合龙,成桥后线形良好,满足设计要求。 相似文献
8.
汕头市牛田洋大桥主桥为(77.5+166.1+468+166.1+77.5) m公轨两用钢桁梁斜拉桥。主桥采用双层桥面布置,上层为双向8车道一级公路兼城市快速路,下层为双线跨座式轨道交通。该桥采用半飘浮体系,纵、横向正交分离的减隔震约束体系。主梁采用带副桁的板桁结合钢桁梁结构,主桁采用三角桁,桁高11 m, 2片主桁中心间距16 m;副桁上弦杆采用平行四边形箱形截面,弦杆顶板中心线间距37.2 m。主梁共63个节间,标准节间长15.1 m,主跨及次边跨公路桥面系采用纵横梁体系正交异性整体钢桥面板,边跨公路桥面系采用纵、横梁支撑的混凝土桥面板;下层轨道交通无桥面板,设置下平纵联。索梁锚固采用锚拉板式钢锚箱。主梁标准节段采用两节间大节段全焊制造。边跨、次边跨钢桁梁采用顶推法施工,主跨钢桁梁采用悬臂吊装法施工。 相似文献
9.
《桥梁建设》2015,(5)
平潭海峡公铁两用大桥元洪航道主桥采用(132+196+532+196+132)m钢桁梁斜拉桥。斜拉桥主梁为带副桁的板桁结合钢桁梁结构,双层桥面布置,上层为6车道高速公路,下层为双线铁路。3号桥塔与主梁间设纵向固定支座,4号桥塔与主梁间设纵向阻尼器。主桁采用N形桁式,桁高13.5m,桁宽15m,标准节间长度14m;副桁架上弦杆顶板中心线间距35.7m。有索区公路桥面及铁路桥面采用密横梁支撑正交异性整体钢桥面结构;无索区公路桥面采用密横梁支撑混凝土桥面结构。在铁路桥面系压重区设封闭钢箱,箱内采用素混凝土集中压重。桥墩处主桁架的竖杆上设置板式桥门架。梁端锚固采用锚拉板结构。该桥采用两节间大节段全焊制造及吊装,最大吊重1 250t,双悬臂架设。 相似文献
10.
《桥梁建设》2019,(6)
平潭海峡公铁大桥大小练岛水道桥为主跨336 m的双塔双索面连续钢桁梁斜拉桥,其主梁为带副桁的板桁结合钢桁梁,采用倒梯形截面。主桁采用N形桁架,桁高13.5 m,主桁中心间距15 m。钢桁梁采用整节段全焊设计,2个节间为1个标准节段。该桥钢桁梁采用全工厂化整节段全焊制造、现场整节段架设方案施工。钢桁梁采用连续匹配方式进行工厂化整节段全焊接制造,首先进行杆件制造,然后进行桁片连续卧拼及桥面板块制造,最后进行节段连续匹配总拼,节段拼装与节段间试拼同时进行。钢桁梁中跨合龙采用整体节段全断面多点合龙技术施工,将合龙段作为1个整体桁段,利用架梁吊机整体提升合龙段,在合龙对位后进行精调,实现海上大型钢桁梁中跨快速、精确合龙。 相似文献
11.
Four methods of erecting steel stiffening truss girder of suspension bridge,including the deck lifting gantry crane method,the cable-mounted crane method,the cantilever erection method with derrick crane and the incremental launching method,were studied Based on construction conditions of the bridge,according to the optimal combination of various factors such as construction safety,quality,period,environmental protection and economic performance,etc,the cantilever erection method with derrick crane was recommended for the bridge. On this basis,three categories of connection in cantilever erection methods,including the all hinged method,the successive fully splicing method and the successive splicing with temporary erection hinge method,were studied The successive splicing with temporary erection hinge method was recommended in the bridge with consideration of the requirements of construction safety,quality and time limit In addition,the traction method of hangers at the top end during cantilever erection was studied Finally,the erection method of three key
stages,including the first segment near the pylon,the standard segment,as well as the closure segment of steel stiffening truss girde,r was studied. The cantilever erection method with derrick crane provides a new way for design and construction of long-span suspension bridge with steel stiffening truss girder in the western area of China 相似文献
12.
坝陵河大桥钢桁加劲梁施工架设方案研究 总被引:3,自引:0,他引:3
首先研究了跨缆吊机架设法、缆索吊机架设法、桥面吊机悬臂拼装架设法和顶推架设法’4种悬索桥钢桁加劲梁施工架设方法,根据坝陵河大桥的建设条件,综合考虑施工安全、质量、工期、环保和经济性等因素,推荐采用桥面吊机悬臂拼装架设法。在此基础上,研究了钢桁加劲梁在悬臂拼装过程中的3种连接方式:全铰法、无铰逐次刚接法和有铰逐次刚接法,综合考虑施工安全、质量和工期要求,推荐采用有铰逐次刚接法。此外,研究了钢桁加劲梁在悬臂拼装过程中架设前端吊索的牵引方案。最后,研究了靠索塔首次节段、标准节段以及合龙段等3个关键阶段的架设方案。桥面吊机悬臂拼装方案为我国西部地区大跨钢桁加劲梁悬索桥的设计和施工提供了1种新的方法。 相似文献
13.
长沙市湘府路快速化改造工程万家丽立交由主线桥和8条匝道组成,共5层,其中主线桥为(60+90+60)m连续梁桥,主梁采用三箱三室变截面钢箱梁;匝道桥主梁采用带悬臂的直腹板钢箱梁。针对该桥钢箱梁施工难点,结合桥址处施工环境,提出了大节段支架法+500 t履带吊架设(方案1)、小节段支架法+260 t履带吊架设(方案2)、双塔吊+260 t履带吊架设(方案3)3种钢箱梁架设方案,通过现场吊装条件、施工难度、工期等方面综合比选,采用方案3施工。该桥钢箱梁分节段制造后,分2期按从下往上的顺序,采用D5200-240塔吊、STT3330-160塔吊和260 t履带吊架设。实践证明采用方案3施工,将施工对城市交通的影响降至最低,解决了地铁交叉施工的问题,满足工期要求。 相似文献
14.
某铁路黄河特大桥为24×48 m上承式钢桁梁桥,建于1969年,因长期服役,梁体安全储备下降,现采用明桥面钢箱梁替换既有钢桁梁.换梁施工采用拖拉法,设置拼装支架、拖拉反力支架、跨线龙门吊等大型临时设施,分别完成钢箱梁拼装、既有钢桁梁拆除及钢箱梁提升上桥;利用PLC同步控制系统和大吨位拖拉牵引系统进行梁体单点单向整体纵向... 相似文献
15.
云南红河特大桥主桥采用单跨700m的悬索桥,加劲梁采用整体式流线型扁平钢箱梁结构,共59个梁段,标准梁段长12m,最大梁段重144.3t。针对桥址区地形陡峻,加劲梁节段运输、吊装难度大等难点,采用缆索吊机吊装加劲梁,缆索吊机跨度布置为(315.2+700+166.1)m,额定吊重160t;设计一套自动化旋转吊具调整加劲梁的方位,以满足吊装纵移空间的要求;斜拉扣挂式墩旁起吊平台由桥塔下横梁墩旁托架、先吊装的端部2个梁段及斜拉扣索组成。端部梁段采用缆索吊机结合纵向牵引荡移装置倾斜吊装;其余梁段利用斜拉扣挂式墩旁起吊平台垂直起吊,从跨中往两岸对称吊装,梁段间采用"全铰法"进行临时连接;合龙段位于两端,利用设于墩旁托架上的三向千斤顶调整对接。 相似文献
16.
17.
连镇铁路五峰山长江大桥主桥为主跨1092 m的钢桁梁公铁两用悬索桥,加劲梁采用板桁结合钢桁梁结构,加劲梁恒载集度大(819.1 kN/m)。其中,一期恒载集度达501 kN/m;铁路桥面和公路桥面二期恒载集度分别为233.4 kN/m和84.7 kN/m。针对该桥特点,加劲梁采用整节段吊装,架设时采用不携带铁路二期恒载的方案施工。边跨加劲梁节段利用浮吊整体吊装至滑移支架上,再滑移至设计位置,连接成整体;中跨加劲梁节段采用2台900 t缆载吊机自跨中向两侧桥塔方向架设,节段间上弦设牛腿式临时铰进行铰接,待中跨80%节段吊装后再进行刚接;中跨加劲梁架设后,对边跨加劲梁整体姿态进行调整,通过顶、落梁与中跨加劲梁合龙,合龙后铺设铁路二期恒载。 相似文献
18.
19.
杭瑞高速洞庭湖大桥位于长江水道之上,桥梁设计为双塔双跨钢桁架梁悬索桥,主桥跨径组合为:460 m+1 480 m+491 m。主桥为钢桁梁结构,钢桁梁的吊装采用缆索起重机施工。受限于现场通航及塔机起重能力,缆索起重机在现场安装困难,故需研究缆载吊机在桥梁主缆索上的散拼安装工艺方案。介绍了LZDJG5000缆载起重机结构的安装思路、重难点以及在施工现场的安装工艺、步骤方案,为类似项目提供借鉴。 相似文献
20.
松浦大桥主桥为两联96m+112m公铁两用钢桁架桥,上层为2车道公路,下层为单线铁路,新金山铁路建成后,对该桥进行改造,其中上层设置为双向6车道公路,需将既有12m宽桥面板更换为24.5m宽钢-混组合正交异性桥面板(单块标准段尺寸为8m×24.5m,重约100t)。受桥梁施工区域黄埔江航道、邻近铁路等因素影响,提出"水上提升站+架板机"、"浮吊+架板机"、"全浮吊"3种新桥面板吊装方案,通过比选采用"全浮吊"方案,即新桥面板采用驳船运至现场,在铁路封锁期内单侧航道间断封航,利用桥位上游侧1艘300t浮吊吊装。施工时,通过设置安全作业区(分南、北侧2个施工区域),合理地进行水上交通组织以及4种船舶锚泊布置,采用装配式固定扒杆浮吊四点起吊新桥面板,安全、快速地完成全部新桥面板更换施工。 相似文献